An MRP implementation checklist
A practical checklist covering data readiness, configuration, testing by role, cutover and the first weeks after go-live.
This is a first draft awaiting review by somebody who runs a factory. It is published as a working document rather than as advice.
Before you choose anything
- Write down the three questions you cannot answer today. They are what the system is for.
- Measure those three things now, however roughly, so there is a baseline.
- Find out who owns each spreadsheet and what is in it that nobody else knows.
- Decide what is deliberately staying where it is: accounts, CAD, payroll.
Data readiness
- Parts: one record per part, with the duplicates that accumulated over the years resolved.
- Bills of material: checked against what is actually built, level by level.
- Routings: operations in the right order with times that are approximately right.
- Suppliers: lead times that reflect reality, and minimum order quantities where they exist.
- Stock: counted, agreed and signed off, not estimated.
- Open orders: sales and purchase, with the dates currently promised.
- Work in progress: what is on the floor part-finished, and how far through it is.
Configuration
- Sites, work centres and the calendars they actually run.
- Roles and permissions matched to jobs, not to seniority.
- Numbering that matches what people already say out loud.
- Forms and documents that customers will see.
Testing
- Each role works a full day of their own work, on the devices they use.
- One complete job from enquiry to despatch, with quantities and costs reconciled at every step.
- A deliberate mistake, corrected, to see what the audit trail records.
- A restore from backup, timed and recorded.
Cutover and after
- A date, a fallback, and everyone knowing what the fallback is.
- Opening stock and open orders loaded and reconciled before the first day.
- Somebody on site or immediately reachable for the first week.
- A review at four weeks against the three questions you wrote down at the start.
What this does not cover
This is a general checklist. It does not cover integration testing, multi-site cutover, or regulated industries where validation requirements apply.
How an implementation runs · Moving from spreadsheets to MRP